CASE STUDIES

LARGE MANHOLE INSTALLATION

ABOUT THE PROJECT The contractor was able to install the manholes efficiently reducing the interruption to area businesses. The contractor chose Shea Concrete Products because we were able to deliver in the time frame needed and deliver a quality product.

Read More

BOAT RAMP INSTALLATION

ABOUT THE PROJECT The contractor was able to install the precast panels and not be concerned about pouring the boat ramp sections during tidal conditions. This allowed the contractor to work all day even when the tide was approaching the

Read More

RETAINING WALL INSTALLATION

ABOUT THE PROJECT Shea Concrete was able to provide a wall system in heights exceeding 14 feet without the use of geo-grid. Shea Concrete was also able to deliver the material in a quick enough time frame to meet the

Read More

PUMP CHAMBER & SEPTIC TANK INSTALLATION

ABOUT THE PROJECT The contractor was able to finish the pump chamber promptly and reduced the cost of maintaining an excavation during high water table and severe weather conditions. STRUCTURE DESCRIPTION The project consisted of installing a Pump Chamber 96” ID x

Read More

SEA WALL INSTALLATION

ABOUT THE PROJECT Work on the project began in the summer of 2011. Removal of the existing wall was followed by the excavation of a trench for a footing. Ocean Avenue remained open and untouched during the construction of the

Read More

CULVERT INSTALLATION Process

ABOUT THE PROJECT Upon its arrival at the job site, contractors seamlessly laid the boxed culvert into place where it now can serve the function of facilitating proper drainage in the surrounding area. “This project showcases the capabilities and drive

Read More

UNDERGROUND DETENTION SYSTEM

ABOUT THE PROJECT Another concept evaluated was the use of 48” diameter HDPE (a competing product), which uses an expensive manifold design, and a larger footprint with more cover than required by Precast Concrete Chambers to maintain H-20 Loading. Using

Read More
Scroll to Top